Project
Name |
| Fabrication and Erection of Raw Material Conveyor Handling System, Taichung |
|
Client |
| Dragon Steel Corporation |
|
Weight |
| 25896 tons |
|
Construction
Period |
| From
January, 2007 to April,
2010 |
|
Location |
| Taichung, Taiwan |
|
|
| |
|
|
| |
|
| |
| |
|
| |
 |
| |
|
Project
Name |
| Conveyor System for Raw Material Handling of CSC, Kaohsiung |
|
Client |
| CSC |
|
Weight |
| 5,600 tons |
|
Location |
| Kaohsiung, Taiwan |
|
|
| |
|
|
| |
|
| |
| |
|
| |
 |
| |
|
Project
Name |
| 2
Sets of Stacker-reclaimer
for CSC 4th Expansion Project. |
|
Client |
| China
Steel Co., Ltd. |
|
Weight |
| 886
metric tons |
|
Construction
Period |
| From
February, 1995 to September,
1995 |
|
Location |
| Kaohsiung, Taiwan |
|
|
| |
|
|
| |
|
| |
| |
|
| |
 |
| |
|
Project
Name |
|
2 Sets of Ship Unloader for
CSC 4th Expansion Project. |
|
Client |
| Kocks,
Germany |
|
Weight |
| 1,775
metric tons |
|
Construction
Period |
| From
October, 1994 to December,
1995 |
|
Location |
| Kaohsiung, Taiwan |
|
|
| |
|
|
| |
|
| |
| |
|
| |
 |
| |
|
Project
Name |
| Stacker-reclaimer
for Taichung Power Plant |
|
Client |
| MAN
GHH, Germany |
|
Weight |
| 1,230
metric tons |
|
Construction
Period |
| From
January, 1994 to October,
1994 |
|
Location |
| Taichung, Taiwan |
|
|
| |
|
|
| |
|
| |
| |
|
| |
 |
| |
|
Project
Name |
| Coke
Oven Machie for CSC. |
|
Client |
| Krup-Koppers,
Germany |
|
Weight |
| 1,325metric
tons |
|
Construction
Period |
| From
October,1985~March, 1987 |
|
Location |
| Kaohsiung, Taiwan |
|
|
| |
|
|
| |
|
| |
| |
|
| |
 |
| |
|
Project
Name |
| 40T
Container Crane for Pier 403,
Kaohsiung Harbor |
|
Client |
| Kaohsiung
Harbor Bureau |
|
Weight |
| 540
metric tons |
|
Construction
Period |
| From
February, 1985 to April, 1986 |
|
Location |
| Kaohsiung, Taiwan |
|
|
| |
|
|
| |
|
| |
| |
|
| |
 |
| |
|
Project
Name |
| 40T
Gantry Crane |
|
Client |
| China
Steel Co., Ltd |
|
Weight |
| 130
metric tons |
|
Construction
Period |
| From
June, 1981 to April, 1982 |
|
Location |
| Kaohsiung, Taiwan |
|
|
| |
|
|
|
|
 |
|
 |
|