Project Name
TSMC Fab14, Taiwan Semiconductor Manufacturing Co., Ltd.
Client
Taiwan Semiconductor Manufacturing Co., Ltd..(TSMC)
Weight
14,300 metric tons
Construction Period
From October of 2002 to December of 2003
Location
Tainan Scientific Park, Taiwan
 
   
 
   
 
Project Name
Fab. I and Fab. II Grace Semiconductor Manufacturing Corporation
Client
CORE PACIFIC OVERSEAS LIMITED
Weight
17,470 metric tons
Construction Period
From September of 2001 to March of 2002
Location
Shanghai, China
 
   
 
   
 
Project Name
Steel Structures fabrication and Installation of Gueiyu’s Steel Factory
Client
Gueiyu Enterprise
Weight
13,000 metric tons
Construction Period
From November of 1996 to June of 1997
Location
Taichung, Taiwan
 
   
 
   
 
Project Name
Tong Yuan CRT Factory
Client
Tong Yu Construction & Development Co., Ltd.
Weight
10,660 metric tons
Construction Period
From June, 1996 to December, 1996
Location
TaoYuan, Taiwan
 
   
 
   
 
Project Name
IC-3 Plant and Office Building Structures.
Client
United Microeletronics Corporation(UMC)
Weight
25,000 metric tons
Construction Period
From January, 1996 to October, 1996
Location
Hsinchu, Taiwan
 
   
 
   
 
Project Name
No. 3 Plant and Office Building Structures.
Client
Taiwan Mosel Vitelic Inc.
Weight
21,800 metric tons
Construction Period
From October, 1995 to June, 1996
Location
Hsinchu, Taiwan
 
   
 
   
 
Project Name
No. 4 Blast Furnace Structures of China Steel
Client
Davy McKee, UK
Weight
2,850 metric tons
Construction Period
From February, 1995 to September, 1995
Location
Kaohsiung, Taiwan
 
   
 
   
 
Project Name
Silicon Wafer Factory Structure
Client
Taisil Electronic Materials Corporation
Weight
7,340 metric tons
Construction Period
From January, 1995 to July, 1995
Location
Hsinchu, Taiwan
 
   
 
   
 
Project Name
Tonyi TMBP Plant Structure
Client
Tonyi Corporation
Weight
11,401 metric tons
Construction Period
From September, 1993 to March, 1995
Location
Tainan, Taiwan
 
   
 
   
 
Project Name
No. 5 ~ 8 Boiler House Structures of Taichung Power Station.
Client
Taipower Company
Weight
30,800 metric tons
Construction Period
From September, 1992 to June, 1995
Location
Taichung, Taiwan
 
 
 
 
‧Headquarters: No.1, Chung-Kang Rd., Hsiao-Kong, Kaohsiung 81207, Taiwan (China Steel Structure Co., Ltd.)
Tel: 886-7-802-3433  Fax: 886-7-801-9150
‧Taipei Office: Room A, 28F., No.7, Sec. 5, Sinyi Rd., Sinyi District, Taipei 110, Taiwan (Taipei 101 Floor
Building ) Tel: 886-2-8101-0534 Fax: 886-2-8101-0526
‧Tainan Guantian Factory: No.2, Gongye S. Rd., Guantian Industrial Park Service Center, Guantian, Tainan
County 720, Taiwan (R.O.C.) Tel: 886-6-698-6651  Fax: 886-6-698-4820
‧Chung-Kang Steel Structure(KunShan) Co., Ltd.: No. 168, Shuanghua Rd., Huaciao Township, Kunshan City,
Jiangsu Province, China Tel: 86(0512) 5760-5788 Fax: 86(0512) 5760-5969